LiftUp Hosting - Move to Full Rack – Maintenance details
All systems operational
Move to Full Rack
Completed
Scheduled for 02 Feb, 2024 at 10:30 AM – 9:12 PM
Affects
AS136582 Networking
Under maintenance from 10:30 AM to 9:12 PM
AU Core Router
Under maintenance from 10:30 AM to 9:12 PM
VPS Hosting
Under maintenance from 10:30 AM to 9:12 PM
Sydney 02
Under maintenance from 10:30 AM to 9:12 PM
Web Hosting
Under maintenance from 10:30 AM to 9:12 PM
AU Web Hosting
Under maintenance from 10:30 AM to 9:12 PM
Updates
Completed
02 Feb, 2024 at 9:12 PM
Completed
02 Feb, 2024 at 9:12 PM
We've completed our rack move.
We do have some growing pains to work though, such as our limited network capacity due to some issues that occurred. We'll work through them proactively and without interruption to your service
Update
02 Feb, 2024 at 4:08 PM
In progress
02 Feb, 2024 at 4:08 PM
We've got all of our hardware moved accross and have networking restored. We are in the process of turning all of our servers back on
In progress
02 Feb, 2024 at 1:16 PM
In progress
02 Feb, 2024 at 1:16 PM
Now in progress
Planned
02 Feb, 2024 at 10:30 AM
Planned
02 Feb, 2024 at 10:30 AM
Our co-location partner is upgrading the rack to a full rack from a half, and as such we will have to move our equipment. This is directly across and should be a relatively quick and straightforward process.
We are allowing upto 4 hours of total downtime during the move in case we have unexpected issues or we start/finish later, however, expect to be done within an hour